1. JWEMC is responsible for installing all transformers and metering.
  2. 200 Amp services will utilize plug-in meters and the customer/developer is responsible for providing and installing the plug-in meter base.
  3. 400 to 600 Amp services will utilize bolt-in meters and the customer/developer is responsible for providing and installing the bolt-in meter base.
  4. 800 Amp services and above will be secondary CT metered and JWEMC is responsible for furnishing all of the necessary equipment for the metering facility.
  5. If metering is via a plug-in or bolt-in meter base, customer/developer is responsible for providing and installing grounding using an 8 feet copper or copper-clad ground rod at the meter point. On CT meter jobs, JWEMC will install the grounding at the meter.
  6. If metering is via a plug-in or bolt-in meter base, the meter base is to be mounted such that the center of the meter is approximately 5 feet above ground.
  7. On plug-in or bolt-in meter jobs, if the main breaker is more than 10 feet from the meter then a suitable disconnect switch must be mounted immediately adjacent to the meter base.
  8. Customer/developer is responsible for providing a concrete transformer pad per JWEMC construction specifications as necessary for 3-phase transformers. JWEMC will provide the pad for all single-phase transformers.